In a committee hearing Tuesday, Texas senators were furious that natural gas companies wonāt have to better prepare their facilities for extreme weather before this winter and rebuked the Texas Railroad Commission, which regulates the stateās massive oil and gas industry, for not fixing the problem sooner.
Recommended Videos
āWait a minute,ā state Sen. Robert Nichols, R-Jacksonville, told Wei Wang, executive director of the Railroad Commission. āYou havenāt done it yet?ā
But the āloopholeā that lawmakers spent the hearing condemning and the slow timetable for winterizing the state power grid were part of legislation they approved during the regular legislative session in the spring.
Gov. Greg Abbott made weatherizing the stateās electricity generation infrastructure an emergency priority immediately after Februaryās deadly winter storm, which left millions without power for days in freezing weather and caused the deaths of 700 Texans, according to a BuzzFeed News analysis.
In June, Abbott signed bills lawmakers had approved aimed at ensuring the weatherization process happened. At the time, Abbott said āeverything that needed to be done was done to fix the power grid.ā
Senate Bill 3, which Abbott signed into law, calls for creating a committee to map out the stateās energy infrastructure by September 2022, then gives the Railroad Commission 180 days to finalize its weatherization rules.
On Tuesday, lawmakers on the Senate Business and Commerce Committee were frustrated that the new law allows natural gas companies to opt out of weatherization requirements if they donāt voluntarily declare themselves to be ācritical infrastructureā with the state.
They also criticized the timelines laid out by the legislation they approved earlier this year and by the rule-making process now underway at the Railroad Commission that has made weatherizing the stateās natural gas system ā a key component of the power grid ā a slow, frustrating task.
Senators told Wang they want the Railroad Commission to move more quickly to require gas companies to weatherize their equipment.
āI recognize the urgency,ā Wang said.
āI donāt think you do,ā said state Sen. Donna Campbell, R-New Braunfels.
Energy experts said lawmakers have themselves to blame if they wanted the stateās natural gas infrastructure, which sends fuel to many of Texasā largest power plants, to be weatherized quickly ā or at all.
āThe Legislature left this loophole open,ā said Doug Lewin, an Austin-based energy and climate consultant.
Wang told the committee that the Railroad Commissionās proposed rule to implement weatherization standards āmirrors the language in SB 3.ā That didnāt stop senators from demanding immediate action by the commission.
āWeāre not going to mince our words. Iām going to start naming railroad commissionersā names if itās required,ā state Sen. John Whitmire, D-Houston, told Wang. āAnd your job ought to be at stake.ā
Campbell, who at one point Tuesday threatened to shake up the Railroad Commissionās responsibilities, asked Wang: āWhy are you not demanding that [natural gas companies] prepare if theyāre one of the players?ā
Senators asked Wang whether his agency needed better clarity from the Legislature in carrying out the weatherization process, and if so, they would ask Abbott to add the issue to the ongoing special session agenda. Only the governor has the ability to add items to special session agendas, and this session is the only one planned before 2023.
The stateās largest power generation company, Vistra Corp., has begun weatherizing its infrastructure, Vistra senior vice president Amanda Frazier told senators. But the company relies heavily on buying natural gas from other companies to fuel its power plants.
āSo youāre weatherizing your plants, but your fuel supply is not?ā Nichols asked Frazier during Tuesdayās hearing.
āItās an enormous concern of ours,ā Frazier said.
After the hearing, Campbell said the Railroad Commission now has a āgreat opportunityā to quickly weatherize the natural gas industry and said if the agency fails, that job could be given to the stateās Public Utility Commission.
āI donāt know, but itās going to be looked at, so you better prove up your worth and your value,ā Campbell told Wang.
The 2021 Texas Tribune Festival, the weeklong celebration of politics and policy featuring big names and bold ideas, wrapped on Sept. 25, but thereās still time to tune in. Explore dozens of free, on-demand events before midnight Thursday, Sept. 30, at tribfest.org.